CM FOR BULKING STATION - SINARMAS
KLIEN
SINARMAS AGRO RESOURCES & TECHNOLOGY TBK.
LOKASI
TARAHAN, LAMPUNG
KATEGORI PROYEK
ONSTRUCTION MANAGEMENT
DURASI PROYEK
MAY 2024 - APRIL 2025
NILAI PROYEK
IDR 3,000,000,000
CM FOR BULKING STATION - SINARMAS
The project entails the supervision and quality control of the construction of a bulking station in Central of Kalimantan, covering civil, mechanical, electrical, and architectural works
Scope :
Land Clearing
- Grading
- Bulking
- Main Office
- Construction New Jetty
- Utility
- Infrastructure
- Mechanical and electrical works
Fabrication & Field Erected 6 Storage Tanks :
4 Unit Palm Oil Storage Tank Cap 5.000 MT
2 Unit Palm Oil Storage Tank Cap 3.000 MT
Stakeholder
PROJECT GALLERY
BIRD’S-EY VIEW OF BULKING STATION PROJECT
STEEL STRUCTURE UTILITY BUILDING