PMC FOR TDAE PLANT 170,000 MT - ENERCO RPO

KLIEN
PT Enerco RPO International
LOKASI
BATAM
KATEGORI PROYEK
PROJECT MANAGEMENT & CONSULTATNCY SERVICES
DURASI PROYEK
MAY 2018 - JUNE 2021
NILAI PROYEK
IDR 24,000,000,000

PMC FOR TDAE PLANT 170,000 MT - ENERCO RPO

Scope :

Enerco is the pioneer of TDAE plant in Indonesia, utilizing its own unique technology. This presented additional challenge, as we had no predecessor in constructing the TDAE Plant.

We successfully completed the construction of the plant on-time, on-budget, and proudly exceeded the designed performance.

Project Management and Consultancy Services
  • Status and progress project evaluation
  • Bidding process
  • Assistance during commissioning and start-up phases
  • Technical marketing support
  • Lead regular maintenance activities
Challenges
  • Initial schedule from October 2017 – April 2019 (18M)
  • Status as per April 2018: progress 26% (lag 16%)
  • Dispute with sub-contractors in term of scope of work and budget.
  • Assisting CESCO for chemical cleaning
Stakeholder
Result of Hard Work
  • LTI Zero
  • Mechanical Completion achieved on end March 2019