JAMBARAN TIUNG BIRU PROJECT (JTB)

KLIEN
PT PERTAMINA EP CEPU
LOKASI
BOJONEGORO
KATEGORI PROYEK
CONSTRUCTION, PRE-COMMISIONING
DURASI PROYEK
JANUARY 2021 - SEPTEMBER 2021
NILAI PROYEK
IDR 50,000,000,000

JAMBARAN TIUNG BIRU PROJECT (JTB)

Rapid is responsible for managing pipeline works, starting from site preparation onto commissioning. We employ a high-performing project management team to tackle any technical and social issues that may arise during project execution.

We deliver quality by collaborating with our partners on electrical and instrumentation works, ensuring perfect quality of works for the project owner.

Scope :
  • Site Preparation and Civil Work

  • Pipeline Works

  • River & Road Crossing Works

  • Mechanical Installation

  • Electrical & Instrument Works

  • Pre-commissioning & Testing

Stakeholder
We’re working on this project from
site preparation
until
pre-commisioning
Gathering Pipeline consists of
1.53 km 20” Pipeline
5.26 km 18” Pipeline
with total
9,397 DI
SPECIFICATION HIGHLIGHTS
Coated with
3-Layer Polypropylene Coating
easier to fabricate, and more corrosion resistant and heat resistant than carbon steel
Using exotic material
INCOLOY 825
That’s easier to fabricate, and more corrosion resistant and heat resistant than carbon steel
Welded with both
GTAW and SMAW
Electrical Works
  • 17,60 km FO Cable size 48C
  • 9,20 km Power Cable 3C-95 mm2
  • 5,12 km Power Cable 3C-70 mm2
  • Cathodic Protection installed on the pipeline to prevent rust and corrotions
Mechanical Works
  • 1 Unit Pig Launcher & 2 Units Pig Receiver Installation
  • 47 pcs Spool Bolting
  • 525 EA of Valves (Gate, Ball, Globe, Check, DBB, Control Valves) sizes ranging from ½” up to 18”

PROJECT GALLERY

PIPE NEAR THE FACILITY

PIPE NEAR THE FACILITY

PIPE STRINGING

PIPE STRINGING

PIPE LOWERING

PIPE LOWERING

PIPE WELDING

PIPE WELDING

WELL INSPECTION

WELL INSPECTION

PIPE LINEUP

PIPE LINEUP